City of San Angelo Street Report for September 2021

Local News

SAN ANGELO, Texas – The City of San Angelo released the Street Report for September 2021, covering the progress of active street projects, upcoming street projects and street maintenance projects throughout San Angelo, according to a statement from the City of San Angelo on Wednesday.

Below is a list of Active Street Projects throughout the City of San Angelo:

  • Winter Storm Street Repairs
    • Repairs: 90% Complete
  • Bell Street (on track to be completed by December 2021, ahead of schedule)
    • Construction Type: Reconstruction of roadway, relocation/replacement of utilities
    • Cost: $22 million
      • Utility rehabilitation: $12 million
      • Roadwork: $10 million
    • Current Status:
      • Utility rehabilitation – 100% complete
        • Utilities: completed
      • Roadway Construction – 90% complete
        • Curb & sidewalks: Poured up to Roosevelt St.
        • Paving: Poured up to Bryan St.
    • Contractor: Reece Albert Inc.
  • Downtown Chadbourne Street (estimated 18 month project)
    • Construction Type: Reconstruction of roadway, rehabilitating aging utilities, improving pedestrian safety and access
    • Cost: $7.6 million
    • Current Status:
      • Chadbourne Street from the Concho River to Beauregard
        • Street Construction: 99% complete
        • Sidewalk construction: 100% complete
        • Traffic Signals, lighting: 25% complete
      • Landscaping was delayed due to availability of plants after the winter storm in February. This should begin mid-to-late September, according to the City of San Angelo.
      • Work on the traffic signals is underway.
      • The Twohig and Chadbourne intersection is still closed due to franchise utility work
    • Contractor: TiZack Concrete Inc.
  • North Chadbourne Street from Loop 306 to 43rd Street
    • Construction Type: Reconstruction of roadway
    • Current Status:
      • Water main replacement: 100% complete
      • Sewer main replacement: 15% complete
      • Street portion – Nearing bidding stage
  • Southwest Boulevard: (estimated completion date is April 2022)
    • Construction Type: Mill and overlay, drainage and reconstruction work
    • Cost: $5.9 million
    • Current Status:
      • Mill and overlay sections complete
      • Work continues on the Southwest Boulevard low water crossing near McDonald’s. Barring any weather delays, this should be completed in September.
      • The reconstruction of the Southwest/Southland intersection is underway and will be completed in approximately 10-12 weeks.
      • Reconstruction of Southwest Boulevard from the low water crossing near Tractor Supply to Loop 306 is still ongoing. During this time, citizens may see closures of traffic lanes and detours. Please use caution in these areas and pay attention to traffic signage.
    • Contractor: Reece Albert Inc.

Future Street Projects for the City of San Angelo

  • Chadbourne Street (Avenue L to Avenue B)
    • Construction Type: Reconstruction of roadway
    • Design Phase: In progress
  • College Hills (from Loop 306 to Avenue N)
    • Construction Type: Reconstruction of roadway, drainage work, underground utilities, signalized intersection upgrades and ADA-compliant sidewalks and ramps.
    • Design Phase: 90% complete
      • Council recently approved $8 million from the American Rescue Plan Grant to fund the installation of an underground drainage structure from behind Goodwill to the Red Arroyo.
  • Edmund/Glenna/29th Street
    • Construction Type: Mill and overlay, reconstruction of roadway, utility rehabilitation
    • Design Phase: In progress
  • Howard Street
    • Construction Type: Mill and overlay. Engineering firm will be pulling core samples from roadway to verify what is under the roadway and its current condition.
    • Design Phase: In progress
  • Jackson Street (Knickerbocker Road to Railroad Tracks)
    • Construction Type: Reconstruction of roadway
    • Design Phase: 75% complete
  • Rio Concho Drive
    • Construction Type: Full depth reclamation (FDR) of the roadway
      • City staff will be going to Council on Thursday, September 9th with a recommendation to award the project
  • Sunset Drive (from Loop 306 near Academy to Foster Road)
    • Construction Type: Mill and overlay
    • Estimated Cost: $11.8 million
      • Street Portion – $4.75 million
      • Utilities Portion – $7 million
    • Design Phase: Work will be contracted for design in late 2021
  • Other Future Projects
    • East Harris Street
    • Johnson Street
    • Christoval Road
    • S. & W. Washington Street
    • Avenue N
    • Smith Boulevard

Street Maintenance Projects in San Angelo

  • Projects performed annually as preventative maintenance procedure for City Streets
    • 2021 Sealcoat Project – Completed in August
      • College Hills area adjacent to Southwest Boulevard & Sunset Drive
      • Southland Boulevard from Sam’s Club to Bermuda Drive
      • Stone Canyon Trail from Ridgecrest Lane to Walnut Drive
      • School House Drive
      • Twin Mountain Drive from Massenburg Drive to Knickerbocker Road
      • Lake area adjacent to KOA, Middle Concho & Hot Water Slough parks
      • South Concho Drive from Knickerbocker Road to Las Lomas Drive
    • GSB-Friction Seal Surface Treatment – Completed in June
      • Green Acres area
      • Rio Concho West (off Hwy 2288)
      • Southridge subdivision
    • High Density Mineral Bond (HA5) – completed in June
      • Southland area
        • Ridgecrest Lane to Walnut Hill Drive
        • Canyon Rim Drive to Stone Canyon Trail
        • Canyon Rim Drive to Southland Boulevard
        • Shefflera Drive to Royal Oak Drive
        • Grandview Drive, Clearview Drive, Scenic Vista Drive, Champions Circle
      • Portion of Bentwood
      • The Palms Area

Completed Street Projects

  • 2017
    • MLK Boulevard – Reconstruction and relocation of utilities
    • Southland Boulevard – Widened from Sherwood Way to Walmart traffic light
  • 2018
    • College Hills Boulevard – Repaved from Loop 306 to Valleyview Drive
  • 2019
    • West Concho Avenue – Widened and reconstructed asphalt roadway with concrete; installed new utilities
  • 2021
    • Southwest Boulevard – Mill an overlay portion

For more information about the September 2021 Street Report, click here.

Copyright 2021 Nexstar Media Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.